I am taking this Adjournment matter on behalf of my colleague, the Minister for Education and Science, Deputy Batt O'Keeffe. I thank the Senator for raising this matter as it provides me with an opportunity to outline to the Seanad the Government's strategy for capital investment in educational projects as well as outlining the current position concerning St. Laurence O'Toole national school in Dublin 1.

Modernising facilities in our existing building stock as well as the need to respond to emerging needs in areas of rapid population growth is a significant challenge. The Government has shown a consistent determination to improve the condition of our school buildings and to ensure the appropriate facilities are in place to enable the implementation of a broad and balanced curriculum.

The allocation of funding for school buildings in 2010 is a little under €579 million. This represents a significant investment in the schools building and modernisation programme. This level of funding, at a time of great pressure on public finances, is a sign of the Government's commitment to investing in school infrastructure. It will permit the continuation of the Department's programme of sustained investment in primary and post-primary schools.

All applications for capital funding are assessed in the Department's planning and building unit. The assessment process determines the extent and type of need presenting based on the demographics of an area, proposed housing developments, condition of buildings and site capacity, thus leading to an appropriate accommodation solution. As part of this process, a project is assigned a band rating under published prioritisation criteria for large-scale building projects. These criteria were devised following consultation with the education partners. The original criteria were revised and refined in 2004. Projects are selected for inclusion in the schools building and modernisation programme on the basis of priority of need. This is reflected in the band rating assigned to a project. In other words, a proposed building project moves through the system commensurate with the band rating assigned to it.

The project for St. Laurence O'Toole's primary school emerged from a feasibility study commissioned by the Dublin Docklands Development Authority, DDDA, in 2005. The DDDA subsequently came forward with a proposal to the Department to make a significant contribution towards the building costs of the project. The project is being developed jointly by the Department of Education and Science and the Dublin Docklands Development Authority. The DDDA is acting as project manager on this project as it is the primary funding agent. The project has been assigned a priority band rating of 1.4 under the published prioritisation criteria for large-scale building projects.

The project is currently at stage 1, preliminary sketch scheme, which is an early stage of the architectural planning process. As the project is in the early stages of architectural planning, the Department is not in a position to comment further on the details of the funding arrangements or the overall estimated cost of the project as to do so could potentially affect the tendering process for the project at a future stage. I can inform the Senator that the Department of Education and Science has not received any communication from the DDDA regarding potential difficulties in funding the project.

The progression of all large-scale building projects, including this one, from initial design stage through to construction is dependent on the prioritisation of competing demands on the funding available under the Department's capital budget. The proposed building project will be considered in the context of the Department's multi-annual schools building and modernisation programme. However, in light of current competing demands on the Department's capital budget, it is not possible to give an indicative timeframe for the delivery of the project at this time.

I thank the Senator again for giving me this opportunity to outline to the Seanad the current position regarding the school building project for St. Laurence O'Toole national school in Dublin 1.