Adjournment Matters. - Derrybrien Wind Farm.

 

Work was immediately suspended on site following the incident and has not since resumed. All staff and contractors working on the site were fully accounted for and there was no injury to any member of the public. It is too early to determine the implications for the construction and commissioning programme or to determine whether any modifications will be required to the windfarm specifications. Decisions on these items must await the completion of the various investigations now under way.