The amended draft brief submitted to the Department by the board in early 2001 was approved and a suitable site identified on the grounds of St. Ita's Hospital. In 2001, a project team was established and this was followed by the appointment of a design team. In September 2002, approval was given by my Department to proceed to stage 4 – the detailed design stage, drawing up of plans, etc. – and stage 5 – preparation of bills of quantities – of the project. In addition, the board has been given approval to apply for full planning permission. As the Senator indicated, that process has already begun.