Written Answers — Department of Communications, Climate Action and Environment: Broadband Infrastructure (15 Dec 2022)

Ossian Smyth: The National Broadband Plan (NBP) state led intervention will be delivered by National Broadband Ireland (NBI) under a contract to roll out a high speed and future proofed broadband network within the intervention area which covers 1.1 million people living and working in over 560,000 premises, including almost 100,000 businesses and farms along with some 679 schools. There are over 2.47...

Written Answers — Department of Communications, Climate Action and Environment: Broadband Infrastructure (15 Dec 2022) See 4 other results from this answer

Catherine Murphy: 154. To ask the Minister for Communications, Climate Action and Environment if the Government clawbacks in respect of the National Broadband Plan will not be diminished as a result of NBI’s interest in X3T and the expectation from its shareholders; if he has engaged with NBI regarding its interest in the company; and if he is satisfied that no risk arises in respect of his interests in...

Written Answers — Department of Communications, Climate Action and Environment: Broadband Infrastructure (15 Dec 2022) See 1 other result from this answer

Ossian Smyth: ...areas in every county in Ireland, where commercial operators are not already providing a high speed broadband service. The network that is being built and operated by National Broadband Ireland (NBI), is a wholesale open-access network, which means that NBI does not sell services directly to homes, businesses, or organisations such as public sector bodies, but instead makes the network...

Written Answers — Department of Communications, Climate Action and Environment: Broadband Infrastructure (15 Dec 2022) See 1 other result from this answer

Ossian Smyth: The National Broadband Plan (NBP) state led intervention will be delivered by National Broadband Ireland (NBI) under a contract, signed in November 2019 and which came into effect in January 2020, to roll out a high speed and future proofed broadband network within the intervention area which covers 1.1 million people living and working in over 560,000 premises, including almost 100,000...

Written Answers — Department of Communications, Climate Action and Environment: Waste Management (15 Dec 2022)

Ossian Smyth: The National Broadband Plan (NBP) state led intervention will be delivered by National Broadband Ireland (NBI) under a contract to roll out a high speed and future proofed broadband network within the intervention area which covers 1.1 million people living and working in over 560,000 premises, including almost 100,000 businesses and farms along with some 679 schools. High-speed...

Written Answers — Department of Communications, Climate Action and Environment: Broadband Infrastructure (13 Dec 2022)

Ossian Smyth: The National Broadband Plan (NBP) state led intervention will be delivered by National Broadband Ireland (NBI) under a contract, signed in November 2019 and which came into effect in January 2020, to roll out a high speed and future proofed broadband network within the intervention area which covers 1.1 million people living and working in over 560,000 premises, including almost 100,000...

Written Answers — Department of Communications, Climate Action and Environment: Broadband Infrastructure (13 Dec 2022) See 2 other results from this answer

Michael Collins: 192. To ask the Minister for Communications, Climate Action and Environment his views on the fact that some 700 national schools that have been assigned to NBI for the provision of broadband; the costs for these schools in relation to same given that NBI has not provided fibre connectivity to the vast majority of schools and is providing connectivity via wireless technology (details...

Written Answers — Department of Enterprise, Trade and Employment: Departmental Strategies (6 Dec 2022)

Leo Varadkar: ...Plan was impacted negatively by COVID-19, the Department of Environment, Climate and Communications is continuing to engage with National Broadband Ireland to address the delays that have arisen. As a result of actions taken by NBI, the project has been building momentum and month. - The publication of the Civil Service Blended Working Policy Framework by the Department of Public...

Written Answers — Department of Communications, Climate Action and Environment: Broadband Infrastructure (6 Dec 2022)

Ossian Smyth: The National Broadband Plan (NBP) State led Intervention will be delivered by National Broadband Ireland (NBI) under a contract to roll out a high speed and future proofed broadband network within the Intervention Area which covers 1.1 million people living and working in over 560,000 premises, including almost 100,000 businesses and farms along with some 679 schools.I am advised by National...

Written Answers — Department of Communications, Climate Action and Environment: National Broadband Plan (30 Nov 2022) See 1 other result from this answer

Alan Dillon: ...Action and Environment the process for the inclusion of Eircode postcodes that were missed in the original surveys contained within amber intervention areas in the roll-out of the NBP; the average NBI connection time for these premises; and if he will make a statement on the matter. [59610/22]

Written Answers — Department of Communications, Climate Action and Environment: National Broadband Plan (29 Nov 2022)

Ossian Smyth: I am advised by NBI that, as of 18 November 2022, over 107,400 premises can order or pre-order a high-speed broadband connection across 25 counties, with over 95,700 premises passed across 25 counties and available for immediate connection. Construction is underway across 26 counties demonstrating that the project is reaching scale. To date, the level of connections...

Written Answers — Department of Communications, Climate Action and Environment: Postal Services (23 Nov 2022)

Eamon Ryan: ...a broadband service. For example, in the case of the National Broadband Plan, where an Eircode has not been allocated to a premises in the Amber area, I am advised that National Broadband Ireland (NBI) will allocate a temporary reference to a premises so an order can be processed. This temporary identifier will be reconciled with the Eircode when it is allocated. An Post and Ordinance...

Ceisteanna Eile - Other Questions: National Development Plan (15 Nov 2022) See 1 other result from this debate

Michael Moynihan: .... He mentioned broadband. Some of the dates given are in 2024 or 2025 and the roll-out in particular areas has been brought back to 2023. Is there engagement with National Broadband Ireland, NBI, to see whether it can be further speeded up to ensure broadband for rural Ireland? It is the great enabler. There are great prospects for remote working and for companies to set up in rural...

Written Answers — Department of Communications, Climate Action and Environment: National Broadband Plan (9 Nov 2022)

Ossian Smyth: The National Broadband Plan (NBP) State led Intervention will be delivered by National Broadband Ireland (NBI) under a contract to roll out a high speed and future proofed broadband network within the Intervention Area which covers 1.1 million people living and working in over 560,000 premises, including almost 100,000 businesses and farms along with some 679 schools. I am advised by...

Ceisteanna Eile - Other Questions: National Broadband Plan (8 Nov 2022) See 1 other result from this debate

Ossian Smyth: I am advised by NBI that, as of 28 October 2022, over 97,000 premises can order or pre-order high-speed broadband connections. More than 87,700 premises have been passed and are ready for immediate connection. Construction is under way across 26 counties. This demonstrates that the project is reaching scale. NBI has advised that over 3,334 premises in County Louth are passed with a...

Ceisteanna Eile - Other Questions: National Broadband Plan (8 Nov 2022) See 2 other results from this debate

Jennifer Murnane O'Connor: I want to talk about householders in Carlow who contact me every day. A homeowner contacted NBI, the Department and me several times regarding concerns about the change of ownership before a project was completed. He believes he will be forgotten. The original contract specified 200,000 connections by the end of January 2022. The man lives on Coppinaugh Road in Tullow. There are 34...

Written Answers — Department of Communications, Climate Action and Environment: National Broadband Plan (8 Nov 2022)

Ossian Smyth: I am advised by National Broadband Ireland (NBI) that, as of 28 October 2022, over 97,000 premises can order or pre-order a high-speed broadband connection, with over 87,700 premises passed and available for immediate connection. Construction is underway across 26 counties demonstrating that the project is reaching scale. The NBP State led intervention has been designed to re-use...

Written Answers — Department of Communications, Climate Action and Environment: National Broadband Plan (8 Nov 2022)

Eamon Ryan: Survey and design work for the new high speed fibre broadband network under the National Broadband Plan is complete or ongoing by National Broadband Ireland (NBI) in every county in Ireland. I am advised by NBI that, as of 28 October 2022, over 97,000 premises can order or pre-order a high-speed broadband connection across 25 counties, with over 87,700 premises passed across 25 counties and...

Written Answers — Department of Communications, Climate Action and Environment: National Broadband Plan (8 Nov 2022)

Ossian Smyth: Survey and design work for the new high speed fibre broadband network under the National Broadband Plan is complete or ongoing by National Broadband Ireland (NBI) in every county in Ireland. Surveys are needed to establish the condition of existing poles and ducts, to ascertain whether repairs are needed. NBI’s contractors walk the fibre route to inspect infrastructure and gather...

Written Answers — Department of Communications, Climate Action and Environment: National Broadband Plan (8 Nov 2022)

Ossian Smyth: Survey and design work for the new high speed fibre broadband network under the National Broadband Plan is complete or ongoing by National Broadband Ireland (NBI) in every county in Ireland. I am advised by NBI that, as of 28 October 2022, over 97,000 premises can order or pre-order a high-speed broadband connection across 25 counties, with over 87,700 premises passed across 25 counties and...