Public Accounts Committee: 2018 Annual Report of the Comptroller and Auditor General
Chapter 6 - Expenditure under a Maintenance Contract
2019 Appropriation Accounts
Vote 13 - Office of Public Works
(11 Nov 2020)

Brian Stanley: Mr. Buckley can appreciate that almost 300 properties were flooded. Coming into the winter when there may be periods of heavy rainfall people are anticipating the worst, such as heavy rainfall coming down the from Slieve Bloom mountains. Can Mr. Buckley give me a rough idea of when work is likely to start and the length of time it will take to complete the physical works? Were it not for...

Public Accounts Committee: 2018 Annual Report of the Comptroller and Auditor General
Chapter 6 - Expenditure under a Maintenance Contract
2019 Appropriation Accounts
Vote 13 - Office of Public Works
(11 Nov 2020)

Brian Stanley: To save time, can Mr. Buckley revert to me on that?

Public Accounts Committee: 2018 Annual Report of the Comptroller and Auditor General
Chapter 6 - Expenditure under a Maintenance Contract
2019 Appropriation Accounts
Vote 13 - Office of Public Works
(11 Nov 2020)

Brian Stanley: The other scheme I want to mention is the Mountrath scheme. A scheme was put in for Mountrath and it was not backed by the OPW on the basis of value for money. I am very familiar with the area. I crossed it when I was going to school. A weir was constructed there. There were two weirs. One of them was taken out. The remaining one is causing problems. It is increasing the water levels...

Public Accounts Committee: 2018 Annual Report of the Comptroller and Auditor General
Chapter 6 - Expenditure under a Maintenance Contract
2019 Appropriation Accounts
Vote 13 - Office of Public Works
(11 Nov 2020)

Brian Stanley: In the cost benefit analysis can Mr. Sydenham take into consideration the households in Patrick Street, Dunne's Terrace and Stillbrook? It is the residents who are either at risk of flooding or have been flooded in the past.

Public Accounts Committee: 2018 Annual Report of the Comptroller and Auditor General
Chapter 6 - Expenditure under a Maintenance Contract
2019 Appropriation Accounts
Vote 13 - Office of Public Works
(11 Nov 2020)

Brian Stanley: I do not see it as needing very large works. I do not want to simplify it. When the OPW starts doing a job it may turn out to be not as simple as it looks but we are not moving mountains here. It is relatively minor works that need to be carried out on the Whitehorse river. My last question relates to the-----

Public Accounts Committee: 2018 Annual Report of the Comptroller and Auditor General
Chapter 6 - Expenditure under a Maintenance Contract
2019 Appropriation Accounts
Vote 13 - Office of Public Works
(11 Nov 2020)

Brian Stanley: Yes, the two of those. Regarding the works on the Shannon, €7 million was provided for the works roughly in the area of Clonmacnoise down to Lusmagh. I had a response from the witnesses recently on this and that is allocated. I spoke to one man yesterday who has two small houses in Shannon Harbour. Both of them have been flooded. Most of his farmland is under water as we speak....

Public Accounts Committee: 2018 Annual Report of the Comptroller and Auditor General
Chapter 6 - Expenditure under a Maintenance Contract
2019 Appropriation Accounts
Vote 13 - Office of Public Works
(11 Nov 2020)

Brian Stanley: The physical works.

Public Accounts Committee: 2018 Annual Report of the Comptroller and Auditor General
Chapter 6 - Expenditure under a Maintenance Contract
2019 Appropriation Accounts
Vote 13 - Office of Public Works
(11 Nov 2020)

Brian Stanley: I am particularly concerned about Shannon Harbour and Banagher. The people in Shannon Harbour have suffered a great deal from being repeatedly flooded. To confirm what Mr. Buckley is saying, physical works - spades in the ground - on the River Shannon in the area from Clonmacnoise to Lusmagh will happen in 2021.

Public Accounts Committee: 2018 Annual Report of the Comptroller and Auditor General
Chapter 6 - Expenditure under a Maintenance Contract
2019 Appropriation Accounts
Vote 13 - Office of Public Works
(11 Nov 2020)

Brian Stanley: Mr. Buckley might submit a more detailed reply on that as well.

Public Accounts Committee: 2018 Annual Report of the Comptroller and Auditor General
Chapter 6 - Expenditure under a Maintenance Contract
2019 Appropriation Accounts
Vote 13 - Office of Public Works
(11 Nov 2020)

Brian Stanley: I thank Mr. Sydenham.

Public Accounts Committee: 2018 Annual Report of the Comptroller and Auditor General
Chapter 6 - Expenditure under a Maintenance Contract
2019 Appropriation Accounts
Vote 13 - Office of Public Works
(11 Nov 2020)

Brian Stanley: I thank Mr. Bourke. One of the other projects mentioned in the report is the Morrison's Island project in Cork city and I know the delay in that regard is beyond the OPW's control. My understanding is that there are legal proceedings in train, on which I know the witnesses cannot comment. Will this matter be dealt with in the courts shortly? What stage are we at with this? That is one...

Public Accounts Committee: 2018 Annual Report of the Comptroller and Auditor General
Chapter 6 - Expenditure under a Maintenance Contract
2019 Appropriation Accounts
Vote 13 - Office of Public Works
(11 Nov 2020)

Brian Stanley: We have gone a couple of minutes over time. I must watch the Covid-19 regulations. Is Deputy Burke happy to get a written reply from the OPW?

Public Accounts Committee: 2018 Annual Report of the Comptroller and Auditor General
Chapter 6 - Expenditure under a Maintenance Contract
2019 Appropriation Accounts
Vote 13 - Office of Public Works
(11 Nov 2020)

Brian Stanley: We will look for a written reply specifically on that for Deputy Burke. I will ask this briefly because Deputy MacSharry has a question. Deputy Catherine Murphy asked a question near the end of her contribution earlier about the final arbitration cost for Kevin Street Garda station. Will the OPW supply that to her in writing, please?

Public Accounts Committee: 2018 Annual Report of the Comptroller and Auditor General
Chapter 6 - Expenditure under a Maintenance Contract
2019 Appropriation Accounts
Vote 13 - Office of Public Works
(11 Nov 2020)

Brian Stanley: That was the final cost of Kevin Street.

Public Accounts Committee: 2018 Annual Report of the Comptroller and Auditor General
Chapter 6 - Expenditure under a Maintenance Contract
2019 Appropriation Accounts
Vote 13 - Office of Public Works
(11 Nov 2020)

Brian Stanley: I will ask about decentralisation. One of the questions we submitted on the list for today was on the number of premises in Portlaoise the OPW has leased to Departments. What is the number of overall premises owned and leased? Are there plans to consolidate them further? The Department of Agriculture, Food and the Marine at one stage was in seven different locations, some of which were...

Public Accounts Committee: 2018 Annual Report of the Comptroller and Auditor General
Chapter 6 - Expenditure under a Maintenance Contract
2019 Appropriation Accounts
Vote 13 - Office of Public Works
(11 Nov 2020)

Brian Stanley: How many is it in at the moment?

Public Accounts Committee: 2018 Annual Report of the Comptroller and Auditor General
Chapter 6 - Expenditure under a Maintenance Contract
2019 Appropriation Accounts
Vote 13 - Office of Public Works
(11 Nov 2020)

Brian Stanley: Very well. The other question I wish to ask is on the vacant site that was bought for the Department of Agriculture, Food and the Marine on the Mountrath Road. How much was paid for it and what will happen to it now? There are pylons and a power line has now gone across the middle of that site. How much did that site cost? It has been lying idle now for a good few years.

Public Accounts Committee: 2018 Annual Report of the Comptroller and Auditor General
Chapter 6 - Expenditure under a Maintenance Contract
2019 Appropriation Accounts
Vote 13 - Office of Public Works
(11 Nov 2020)

Brian Stanley: Mr. Bourke might give us more information on that. I do not want to get into it now. Will he come back, specifically, with the number of premises occupied by Departments in Portlaoise and the annual cost of the leases on those?

Public Accounts Committee: 2018 Annual Report of the Comptroller and Auditor General
Chapter 6 - Expenditure under a Maintenance Contract
2019 Appropriation Accounts
Vote 13 - Office of Public Works
(11 Nov 2020)

Brian Stanley: Yes, briefly, because I am tied with time.

Public Accounts Committee: 2018 Annual Report of the Comptroller and Auditor General
Chapter 6 - Expenditure under a Maintenance Contract
2019 Appropriation Accounts
Vote 13 - Office of Public Works
(11 Nov 2020)

Brian Stanley: Of course.