- Public Accounts Committee: Appropriation Accounts 2023
Vote 13 - Office of Public Works (22 Oct 2024) Verona Murphy: I thank Mr. Casey. I want to ask about the PR consultant contract in respect of which the tender was withdrawn. Was there a reason for that?
- Public Accounts Committee: Appropriation Accounts 2023
Vote 13 - Office of Public Works (22 Oct 2024) Verona Murphy: Is Mr. Conlon going to reappoint the current consultants for another year? I believe that is allowed.
- Public Accounts Committee: Appropriation Accounts 2023
Vote 13 - Office of Public Works (22 Oct 2024) Verona Murphy: Reports in the newspapers this morning indicate that Mr. Conlon was concerned about his reputation. I am sure he knows this already, but from the public's perspective and from our perspective in the context of value for money, it would be much easier to enhance his reputation if the mistakes made by the OPW are not continued. If we learn from them, Mr. Conlon will not need a PR consultant.
- Public Accounts Committee: Appropriation Accounts 2023
Vote 13 - Office of Public Works (22 Oct 2024) Verona Murphy: Mr. Conlon's statement was very ill-informed. Most of the modular builds constructed by Shomera actually exceed the lifetime he mentioned. My question refers to the modular build. What is encompassed in the 45 sq. m, from a living perspective? Does it include toilets, bedrooms, sitting room, kitchen?
- Public Accounts Committee: Appropriation Accounts 2023
Vote 13 - Office of Public Works (22 Oct 2024) Verona Murphy: That means there are two bedrooms at €442,000. I do not care if it is the most expensive, worst site in the history of the State. There is not a site in Dublin that has cost €289,000 as Mr. Conlon said in reply to Deputy Kelly, for groundworks. It must be remembered, the same preparation occurs for all constructed houses. It takes less time and it does not come in at that...
- Public Accounts Committee: Appropriation Accounts 2023
Vote 13 - Office of Public Works (22 Oct 2024) Verona Murphy: We were at €289 million. Is this the same person who was contracted to provide the modular build? Is a different contractor providing the solar panels?
- Public Accounts Committee: Appropriation Accounts 2023
Vote 13 - Office of Public Works (22 Oct 2024) Verona Murphy: Mr. Conlon, as Chair of the OPW, is telling this committee and the public in general that the final cost of the modular build at an A1 rating, including solar panels fitted, is €442,000.
- Public Accounts Committee: Appropriation Accounts 2023
Vote 13 - Office of Public Works (22 Oct 2024) Verona Murphy: That is not the question. The cost per unit is currently €442,000. Is Mr. Conlon saying that is without the fitting of solar panels? Is it the case that when that is completed, the cost is not going to change?
- Public Accounts Committee: Appropriation Accounts 2023
Vote 13 - Office of Public Works (22 Oct 2024) Verona Murphy: Will the cost change from €442,000 per unit?
- Public Accounts Committee: Appropriation Accounts 2023
Vote 13 - Office of Public Works (22 Oct 2024) Verona Murphy: He expects it to stay the same.
- Public Accounts Committee: Appropriation Accounts 2023
Vote 13 - Office of Public Works (22 Oct 2024) Verona Murphy: That is an undertaking that we have, even though the project is three times over the initial budget. What happened that meant an estimate of €100 million ended up costing nearly three times that?
- Public Accounts Committee: Appropriation Accounts 2023
Vote 13 - Office of Public Works (22 Oct 2024) Verona Murphy: It did not turn out to be much of an emergency response. It took nearly 20 months longer to put the units in place. As for the sites, ere they ever zoned for housing or serviced in any shape or form? Was the figure of €100 million a cost that went out to tender to Sisk or did Sisk come in with that price?
- Public Accounts Committee: Appropriation Accounts 2023
Vote 13 - Office of Public Works (22 Oct 2024) Verona Murphy: Was the figure of €100 million an amount that was tendered or was it the proposed cost of the project given to Sisk?
- Public Accounts Committee: Appropriation Accounts 2023
Vote 13 - Office of Public Works (22 Oct 2024) Verona Murphy: Did Sisk tender for €100 million?
- Public Accounts Committee: Appropriation Accounts 2023
Vote 13 - Office of Public Works (22 Oct 2024) Verona Murphy: It was an open-ended contract.
- Public Accounts Committee: Appropriation Accounts 2023
Vote 13 - Office of Public Works (22 Oct 2024) Verona Murphy: Will Mr. Conlon answer the question I asked, please? If he does not, I will ask the Chair to intervene. Why did Mr. Conlon not seek an extension?
- Public Accounts Committee: Appropriation Accounts 2023
Vote 13 - Office of Public Works (22 Oct 2024) Verona Murphy: Maybe Ms Morrison is aware of why an extension was not sought. Is there anybody present who understands why the planning was not extended?
- Public Accounts Committee: Appropriation Accounts 2023
Vote 13 - Office of Public Works (22 Oct 2024) Verona Murphy: It was not just for an office block.
- Public Accounts Committee: Appropriation Accounts 2023
Vote 13 - Office of Public Works (22 Oct 2024) Verona Murphy: It was just for an office block.
- Public Accounts Committee: Appropriation Accounts 2023
Vote 13 - Office of Public Works (22 Oct 2024) Verona Murphy: An application to alter the permission could have been made.