Results 4,681-4,700 of 8,745 for speaker:Verona Murphy
- Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 13 - Office of Public Works
Chapter 8 - Contract payments in respect of Convention Centre Dublin (15 Dec 2022) Verona Murphy: That is the first that I have heard about it. Trucks are parking on the side of the road. The facility has not been provided in the way that an undertaking was given here at this committee, as well as other meetings of the transport committee. That facility still has not been provided. I ask Mr. O'Connor to give the committee, for the benefit of road safety, the correspondence the OPW has...
- Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 13 - Office of Public Works
Chapter 8 - Contract payments in respect of Convention Centre Dublin (15 Dec 2022) Verona Murphy: That is very important, Mr. Casey, and I appreciate that. What is being done differently so we do not see any loss of life or flooding for 2022? What has changed? What has been done?
- Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 13 - Office of Public Works
Chapter 8 - Contract payments in respect of Convention Centre Dublin (15 Dec 2022) Verona Murphy: Mr. Casey, why was that not done in 2021?
- Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 13 - Office of Public Works
Chapter 8 - Contract payments in respect of Convention Centre Dublin (15 Dec 2022) Verona Murphy: No.
- Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 13 - Office of Public Works
Chapter 8 - Contract payments in respect of Convention Centre Dublin (15 Dec 2022) Verona Murphy: My first question that I asked, which Mr. Casey did not answer, was on what monitoring station was used or do we use. Clearly, it is hourly, according to Mr. Buckley. What station do we look at to see what is happening for the Wexford Bridgetown area? What station tells us that there could be an issue?
- Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 13 - Office of Public Works
Chapter 8 - Contract payments in respect of Convention Centre Dublin (15 Dec 2022) Verona Murphy: It is not in County Donegal.
- Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 13 - Office of Public Works
Chapter 8 - Contract payments in respect of Convention Centre Dublin (15 Dec 2022) Verona Murphy: Does Mr. Buckley know? Does anybody else know? The officials will find the information, as there are 15 people from Mr. Casey's Department here. The fact that we cannot get answers when there are 15 people officials present is gross. If we cannot get an answer then why are 15 people here? Why, in the name of God? It is a farce that an entourage is brought to a meeting of the Committee...
- Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 13 - Office of Public Works
Chapter 8 - Contract payments in respect of Convention Centre Dublin (15 Dec 2022) Verona Murphy: What is pejorative, Mr. O'Connor?
- Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 13 - Office of Public Works
Chapter 8 - Contract payments in respect of Convention Centre Dublin (15 Dec 2022) Verona Murphy: Pardon?
- Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 13 - Office of Public Works
Chapter 8 - Contract payments in respect of Convention Centre Dublin (15 Dec 2022) Verona Murphy: I will return to my question. When it comes to flooding, we seem all the time to be closing the stable door when the horse has bolted. Why do we know what the issue is now? I have spoken to the locals and been there. I spent Christmas Day in Bridgetown and Enniscorthy and my Christmas holidays last year visiting people who were put out of their homes. They were not compensated or restored...
- Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 13 - Office of Public Works
Chapter 8 - Contract payments in respect of Convention Centre Dublin (15 Dec 2022) Verona Murphy: I am asking the one question that Mr. Buckley cannot answer, which is why the OPW did not do this in 2021. Why is it being done after the horse has bolted? From everything I have read, that seems to be the trademark of the OPW. It has happened in Enniscorthy, Blackwater and now in Bridgetown, to a severe degree.
- Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 13 - Office of Public Works
Chapter 8 - Contract payments in respect of Convention Centre Dublin (15 Dec 2022) Verona Murphy: Mr. Buckley would not accept it.
- Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 13 - Office of Public Works
Chapter 8 - Contract payments in respect of Convention Centre Dublin (15 Dec 2022) Verona Murphy: What would Mr. Buckley say about Enniscorthy if he does not accept that? Was he in Enniscorthy last St. Stephen's Day and for the week post Christmas?
- Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 13 - Office of Public Works
Chapter 8 - Contract payments in respect of Convention Centre Dublin (15 Dec 2022) Verona Murphy: Was Mr. Buckley there for the week after last Christmas? Was Mr. Buckley there at any stage?
- Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 13 - Office of Public Works
Chapter 8 - Contract payments in respect of Convention Centre Dublin (15 Dec 2022) Verona Murphy: No, I did not ask Mr. Casey. I asked Mr. Buckley if he was in Enniscorthy for the week after Christmas last year.
- Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 13 - Office of Public Works
Chapter 8 - Contract payments in respect of Convention Centre Dublin (15 Dec 2022) Verona Murphy: No.
- Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 13 - Office of Public Works
Chapter 8 - Contract payments in respect of Convention Centre Dublin (15 Dec 2022) Verona Murphy: I am asking questions that I want answers to.
- Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 13 - Office of Public Works
Chapter 8 - Contract payments in respect of Convention Centre Dublin (15 Dec 2022) Verona Murphy: The OPW criticised the Department of Public Expenditure and Reform about the fact that it did not pass the OPW's scheme and give effect to what it prepared for the Enniscorthy flood relief.
- Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 13 - Office of Public Works
Chapter 8 - Contract payments in respect of Convention Centre Dublin (15 Dec 2022) Verona Murphy: Will Mr. Buckley explain why the OPW was disappointed?
- Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 13 - Office of Public Works
Chapter 8 - Contract payments in respect of Convention Centre Dublin (15 Dec 2022) Verona Murphy: I am familiar with it but Mr. Buckley can explain it for the benefit of the committee.