Joint Oireachtas Committee on Health: Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board (25 Sep 2024)

Neasa Hourigan: That brings me to commissioning. At this committee and others, every time substantial completion is talked about, commissioning has to be added in. We have always talked about six to eight months. Is the board happy with that as a number?

Joint Oireachtas Committee on Health: Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board (25 Sep 2024)

Neasa Hourigan: There is a grey area here, however. There is an overlap in respect of some of the very complex systems such as the MRI machines and CT scanners that live in the substantial completion part. Is that correct?

Joint Oireachtas Committee on Health: Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board (25 Sep 2024)

Neasa Hourigan: Mr. Gunning described how CHI cannot go into the rooms it would have expected to be completed to start its work because they are simply not complete.

Joint Oireachtas Committee on Health: Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board (25 Sep 2024)

Neasa Hourigan: When we are discussing what we call specialist equipment, in Mr. Gunning's opening statement, there was a piece regarding the board and ClearSphere. It says that the radiopharmacy units and stem cell laboratory should be beginning in September. Have they commenced?

Joint Oireachtas Committee on Health: Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board (25 Sep 2024)

Neasa Hourigan: Is that all of them?

Joint Oireachtas Committee on Health: Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board (25 Sep 2024)

Neasa Hourigan: Is ClearSphere starting now or did it start at the beginning of the month?

Joint Oireachtas Committee on Health: Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board (25 Sep 2024)

Neasa Hourigan: In my last two and a half minutes, I will ask for clarity as regards the baseline programme. The last time we talked, we were talking about BAM submitting programmes that were then not accepted by the board. I am trying to get some clarity on the board's opening statement. It outlines the many times the completion date has been pushed out, which we are all aware of, but I am trying to...

Joint Oireachtas Committee on Health: Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board (25 Sep 2024)

Neasa Hourigan: I did, yes.

Joint Oireachtas Committee on Health: Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board (25 Sep 2024)

Neasa Hourigan: Was there a compliant programme in place from July of last year?

Joint Oireachtas Committee on Health: Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board (25 Sep 2024)

Neasa Hourigan: Am I right in thinking that there is still no compliant programme in place between the board and BAM?

Joint Oireachtas Committee on Health: Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board (25 Sep 2024)

Neasa Hourigan: Am I to infer from what the witnesses have told us that the times BAM has tried to change the finishing point were when it was submitting a programme the board felt to be non-compliant?

Joint Oireachtas Committee on Health: Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board (25 Sep 2024)

Neasa Hourigan: The witnesses are describing a process whereby a staff member is working with BAM to agree a compliant programme. When will that come to fruition? Is there a time on the horizon when there will be a compliant programme?

Joint Oireachtas Committee on Health: Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board (25 Sep 2024)

Neasa Hourigan: What is that deadline?

Joint Oireachtas Committee on Health: Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board (25 Sep 2024)

Neasa Hourigan: Is there another deadline on the horizon?

Joint Oireachtas Committee on Health: Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board (25 Sep 2024)

Neasa Hourigan: I will not use all of my time, so the Senator need not worry. First of all, I am not entirely comfortable with describing this as a boilerplate public works contract because it was a two-stage situation that would not be found in every contract. That left us open to perhaps some of the difficulty we find ourselves in now. I want to go back to technical commissioning. Mr. Devine described...

Joint Oireachtas Committee on Health: Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board (25 Sep 2024)

Neasa Hourigan: Yes, right up to substantial completion. Is there anything that is still out to tender?

Joint Oireachtas Committee on Health: Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board (25 Sep 2024)

Neasa Hourigan: Then all the subcontractors and all the specialist people have entirely been-----

Joint Oireachtas Committee on Health: Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board (25 Sep 2024)

Neasa Hourigan: Have most of those tenders happened in the last six months? When did that tender process occur?

Joint Oireachtas Committee on Health: Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board (25 Sep 2024)

Neasa Hourigan: Let us take, for example, the change orders outlined by the board in the additional material. BAM is described as being in a joint venture with ClearSphere tendering for a specialist fit out.

Joint Oireachtas Committee on Health: Update on Construction of New National Children's Hospital: National Paediatric Hospital Development Board (25 Sep 2024)

Neasa Hourigan: When did that occur?