Results 3,201-3,220 of 5,814 for speaker:Alan Dillon

Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 38 - Health
Chapter 12 - Financial Impact of Cyber Security Attack
(9 Feb 2023)

Alan Dillon: Does Mr. Watt have the ratio of beds per population at present?

Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 38 - Health
Chapter 12 - Financial Impact of Cyber Security Attack
(9 Feb 2023)

Alan Dillon: How many beds-----

Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 38 - Health
Chapter 12 - Financial Impact of Cyber Security Attack
(9 Feb 2023)

Alan Dillon: How many additional beds have been delivered since the capacity review?

Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 38 - Health
Chapter 12 - Financial Impact of Cyber Security Attack
(9 Feb 2023)

Alan Dillon: One thousand.

Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 38 - Health
Chapter 12 - Financial Impact of Cyber Security Attack
(9 Feb 2023)

Alan Dillon: On the basis of Mr. Watt's opening statement, the Department provided €426 million in 2021 for additional beds. I will give him a breakdown in that regard: it is 1,046 acute beds at a cost of €205,933 per bed.

Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 38 - Health
Chapter 12 - Financial Impact of Cyber Security Attack
(9 Feb 2023)

Alan Dillon: Is that value for money? How is that broken down?

Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 38 - Health
Chapter 12 - Financial Impact of Cyber Security Attack
(9 Feb 2023)

Alan Dillon: The figure is €205,000. Does the Department do a value-for-money review on each of the beds that have been delivered?

Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 38 - Health
Chapter 12 - Financial Impact of Cyber Security Attack
(9 Feb 2023)

Alan Dillon: Would the Department review that?

Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 38 - Health
Chapter 12 - Financial Impact of Cyber Security Attack
(9 Feb 2023)

Alan Dillon: Does the Department have a process to do that?

Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 38 - Health
Chapter 12 - Financial Impact of Cyber Security Attack
(9 Feb 2023)

Alan Dillon: Maybe the Department can furnish that for the committee.

Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 38 - Health
Chapter 12 - Financial Impact of Cyber Security Attack
(9 Feb 2023)

Alan Dillon: There was a budget of €32 million for 66 critical beds. Each bed cost €787,878. Is that a figure the Department can stand over?

Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 38 - Health
Chapter 12 - Financial Impact of Cyber Security Attack
(9 Feb 2023)

Alan Dillon: Will Mr. Watt give me an understanding of how €13 million was allocated for 139 sub-acute beds? Are they for step-down facilities?

Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 38 - Health
Chapter 12 - Financial Impact of Cyber Security Attack
(9 Feb 2023)

Alan Dillon: Sorry, I am talking about the sub-acute bed situation.

Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 38 - Health
Chapter 12 - Financial Impact of Cyber Security Attack
(9 Feb 2023)

Alan Dillon: I asked for a breakdown with regard to sub-acute beds. Some 139 sub-acute beds were delivered. Will Mr. Tierney give us an understanding with regard to the delivery of sub-acute beds and the 1,250 community beds at a cost of €125 million? I just want to get an understanding. More than 2,601 beds were delivered in total. Is that additional to what is currently in the public domain...

Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 38 - Health
Chapter 12 - Financial Impact of Cyber Security Attack
(9 Feb 2023)

Alan Dillon: What is the target for 2023 for additional beds required?

Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 38 - Health
Chapter 12 - Financial Impact of Cyber Security Attack
(9 Feb 2023)

Alan Dillon: How many critical care beds?

Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 38 - Health
Chapter 12 - Financial Impact of Cyber Security Attack
(9 Feb 2023)

Alan Dillon: How many community beds?

Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 38 - Health
Chapter 12 - Financial Impact of Cyber Security Attack
(9 Feb 2023)

Alan Dillon: I refer to the Department's capital and estates division and the capacity for it to deliver on this. There is a real challenge in the hospital group in my own area with regard to the resources available to deliver projects across all hospital groups and regions. What is the Department doing to strengthen its division with regard to these types of projects? There are considerable budgets,...

Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 38 - Health
Chapter 12 - Financial Impact of Cyber Security Attack
(9 Feb 2023)

Alan Dillon: Yes, but there is frustration with regard to the timeline from the approval of a capital project to when it delivers. I will bring up the emergency department at Mayo University Hospital again. We have a timeline of 60 months for delivery, which is just unacceptable.

Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 38 - Health
Chapter 12 - Financial Impact of Cyber Security Attack
(9 Feb 2023)

Alan Dillon: Any project of less than €50 million should be delivered within five years.