Dáil debates

Wednesday, 21 May 2025

Saincheisteanna Tráthúla - Topical Issue Debate

Water Services

2:50 am

Photo of Christopher O'SullivanChristopher O'Sullivan (Cork South-West, Fianna Fail)

I thank Deputy O’Donoghue for raising this. I know it is frustrating. He has probably tabled parliamentary questions on this and got an answer saying that he cannot get detailed responses in parliamentary questions because it is a responsibility for Uisce Éireann. Therefore, this is a good opportunity to raise it in the Dáil and get a bit more detailed response from the Department. I welcome that. I will go into more detail in the response, but there seems to be several complications – legacy issues inherited by Uisce Éireann. I think concerted effort between the developer and Uisce Éireann is needed to resolve this. What is there seems to be a bit of a mess, which is causing, as the Deputy outlined, many of the issues.

As the Deputy will understand, the supply of public water and the provision of water services in general are matters for Uisce Éireann in the first instance. Uisce Éireann has statutory responsibility for all aspects of water services planning, delivery and operation at national, regional and local levels. The scope, prioritisation and progression of individual projects are matters for Uisce Éireann and approved through its own board and internal governance structures.

Under section 7 of the Water Services (No. 2) Act 2013, neither I nor the Minister, Deputy Browne, have function regarding Uisce Éireann’s specific operations at Ellen's Court. In other words, Ministers cannot get involved in individual projects; that is a matter for Uisce Éireann. However, I have made inquiries for the Deputy, and my understanding from information provided to me is that this matter relates to a water and wastewater connection issue for six houses in Ellen's Court, County Dublin and has been raised directly with Uisce Éireann previously.

Contractors working on behalf of Uisce Éireann undertook some works at the location in November 2023, but their investigation established that connection works could not be completed by Uisce Éireann due to separate works needing to be completed by the developer of the estate on the private side. Engagement has been ongoing with the developer in the interim, with a view to remediating the issues outlined below.

In summary, Uisce Éireann's contractors identified that the wastewater connection for the development had already been made to the wastewater network, contrary to the requirements of the connection agreement. On this basis, the wastewater connection is an unauthorised connection. Further, Uisce Éireann’s contractors also identified that the unauthorised connection to the wastewater network was made directly through an existing storm water pipe, causing very significant damage to the existing storm water network and significantly increasing the risk of flooding in the area. One can see the level of complication and the legacy that has been inherited here. Uisce Éireann understands that the local authority, as the competent storm water authority, has been in touch with the developer as a result, seeking remediation of the storm water network. That absolutely needs to happen.

On the water side, the water pipe installed by the developer is laid directly on top of the wastewater pipe, rendering the installation non-compliant with Uisce Éireann’s relevant standards. While it may be technically feasible to make a water connection to the existing pipe, any such connection will only compound the existing non-compliance issues, including the existing damage to the storm water network. As a result, and pending rectification of the water-wastewater pipe layout to achieve compliance with Uisce Éireann’s relevant standards, it is not possible to proceed with a connection to the water network.

Finally, the Uisce Éireann contractors observed that the development is currently provided with water by way of an exposed onward supply from an existing premises, which is causing water pressure issues both for the existing and new developments and runs the risk of service interruptions for occupants arising from exposure of the pipe to the elements.

Given the unauthorised connections to both the water and wastewater networks, this is now a legal matter for Uisce Éireann. I have requested Uisce Éireann to engage directly with the residents of Ellen's Court to keep them informed of progress. I hope Uisce Éireann does reach out to the residents, as per the response. I directed Uisce Éireann to do that.

The Deputy can see that it is a bit of a mess, and it has been inherited. While I 100% agree with the Deputy that the constituents he represents need answers, connection and for this to be resolved, when developers go about things in such a way, it makes things incredibly difficult, and that has to be acknowledged as well.

Comments

No comments

Log in or join to post a public comment.