Ceisteanna Eile - Other Questions

North-South Interconnector

9:10 pm

Photo of Eamon RyanEamon Ryan (Dublin Bay South, Green Party) | Oireachtas source

The new North-South interconnector, which will allow for the flow of 900 MW of electricity between Ireland and Northern Ireland, will be critical for improving the operation of the all-island integrated single electricity market. It will also help to facilitate the achievement of the goal of generating up to 80% of our electricity from renewable sources by 2030. A resilient and well-connected energy infrastructure is vital for Ireland's economic well-being and the ability to respond to the future needs of energy consumers.

The option of undergrounding the North-South interconnector has been comprehensively assessed on several occasions. Most recently, the key findings from the international expert commission's report of October 2018 was that an overhead line remains the most appropriate option for this critical electricity infrastructure. Notwithstanding this, it was deemed appropriate to carry out a further short review to assess if the overall finding from the 2018 report remained valid. Having requested tenders from a number of grid experts across Europe, two international experts were selected to carry out the study. Work is continuing on the report, which has taken longer than expected, but I understand it is to be finalised shortly. Following receipt of the report, it will be considered, with publication to follow in due course. I expect to receive it within a short few weeks and will then share it with Government colleagues, publish it and have a debate in the House on its contents.

Comments

No comments

Log in or join to post a public comment.