Ceisteanna - Questions - Ceisteanna ar Sonraíodh Uain Dóibh - Priority Questions
National Broadband Plan
9:20 am
Denis Naughten (Roscommon-Galway, Independent) | Oireachtas source
There is a contradiction in what we are being told. We are told that the primary reason for delays in the roll-out is Covid-19. That just does not stack up. There have been ongoing delays in engagement with local authorities, with CIÉ and with Transport Infrastructure Ireland with regard to getting access to infrastructure. That does not seem to be acknowledged by everyone. Why is there a cover-up and failure to acknowledge that?
Will the Minister of State answer a simple question? The single biggest subcontractor that National Broadband Ireland has is Eir. Eir has achieved its timelines last year, in 2021 and is expected to overachieve in 2022. It had to deal with Covid. How could Eir deliver when National Broadband Ireland cannot?