Dáil debates

Thursday, 16 September 2021

Ceisteanna ar Sonraíodh Uain Dóibh - Priority Questions

Road Projects

10:40 am

Photo of Eamon RyanEamon Ryan (Dublin Bay South, Green Party) | Oireachtas source

I mean no disrespect to the Deputy or the residents of Ardee. He is correct, but I wanted to read out the Department's official response so that the full assessment is clear. I will now read the remaining part of that response which, I hope, will give him some of the detailed information he seeks. I will further engage with him in the detail of it.

In January 2018, Louth County Council provided the preliminary overall plan for the scheme to public representatives and to members of the public. Concerns were raised regarding the junction layout and the impacts the scheme might have on local traffic movements. The Deputy will be aware of some of this detail, but it is important to set out the history. Detailed submissions from resident groups were received by Louth County Council and TII. In September 2019, officials from TII, along with Louth County Council, were invited to the Oireachtas Joint Committee on Transport to discuss the issues. I attended that meeting and listened to the full hearing. It was agreed to request the council to undertake a review of the scheme design in advance of progressing the project to build in order that these issues could be fully considered along with matters raised.

A public consultation was held in October 2020 to engage on the emerging preferred junction option for the N52 Ardee bypass. A review of the road design and planning to date, including junction options, planning application issues, an environmental review and compulsory purchase order, CPO, matters, is currently being carried out by technical advisers for Louth County Council, to be completed later this year. In parallel, an environmental impact assessment, EIA, screening report and appropriate assessment, AA, screening report are currently with An Bord Pleanála for review and determination on the proposed amended scheme. The changes to the original scheme include amended junction layouts, additional cycle facilities, flood attenuation and soil management issues.

Subject to the outcome of the review and determination by An Bord Pleanála of the EIA and AA, it is intended to bring the scheme through the Part 8 planning process of the Planning and Development Regulations 2001, as amended. The next step would be to lodge an application with An Bord Pleanála for a further CPO, if needed. On this basis, Louth County Council could be in a position to tender the main construction contract for the scheme in quarter 3, 2022, which could allow a potential construction start date in quarter 3, 2023, with completion in quarter 4, 2025. It should be noted that this would be subject to sufficient funding availability and approval under the public spending code. A total of €8.1 million was incurred on this project up to the end of August 2021.

I mean no disrespect to the Deputy and apologise for the lengthy reply. We have a significant funding problem, but this type of project, which promotes town centres such as Ardee is, to my mind, a real priority. If we can overcome the planning difficulties, I believe funding can be provided.