National Broadband Plan
9:15 pm
Ossian Smyth (Dún Laoghaire, Green Party) | Oireachtas source
The Deputy's first question was on whether the 220,000 homes had been passed. No, but they have been surveyed. The number of homes that have been passed and are ready for connection to broadband is 4,000. The first of those was connected this year in Carrigaline.
The Deputy asked whether the pandemic had delayed the deployment. The answer is "Yes". The original deployment plans for the first year will not be met. However, the deployment plans for later years will be greater. The new contract will define that acceleration.
To clarify, the first stage is the surveying of premises. Later stages eventually arrive at the point where fibre is passing the house. Of those homes, there are 4,000.