Topical Issue Debate

Wastewater Treatment

5:30 pm

Photo of Malcolm NoonanMalcolm Noonan (Carlow-Kilkenny, Green Party) | Oireachtas source

I will revert to the Deputy with a written response on the two specific items she raises. It may well be the case that additional costs are involved at this stage, given the delays to the project but I will provide a written response on that. It is important to note that we will enter into a new cycle of river basin management plans and projects similar to this one must be expedited to improve our water quality status, which deteriorated during the previous plan period. We are all very conscious of that fact.

Plans for the delivery of the Arklow wastewater plant are at an advanced stage. Irish Water has secured the necessary planning, land and licences and the procurement of the construction contract is in the final stage. I am acutely aware of the need to progress the plant to stop the practice of discharging untreated wastewater into the Avoca river, provide a wastewater treatment facility that will comply with all relevant legislative requirements and service the population of Arklow well into the future and improve water quality in the river.

Irish Water expects construction work to begin in the second half of 2021. Together with the Minister for Public Expenditure and Reform, the Minister for Housing, Local Government and Heritage is expediting consideration of the capital commitment consent for a timely decision to support Irish Water’s plans to commence construction. I hope this is of some assurance to the Deputy.

Comments

No comments

Log in or join to post a public comment.