In the year to date, funding of almost €3.4 million has been provided through the landfill remediation programme for the project at Kerdiffstown. It is expected that further funding in the region of €2 million will be drawn down by Kildare County Council by the end of this year.

Following the completion of the 2021 Estimates process last month, I expect to be in a position to allocate funding of €23.5 million to the landfill remediation programme next year to continue the remediation of environmentally-degraded, discontinued landfill sites operated by local authorities and private landfills taken into State ownership. A significant proportion of this overall allocation will be directed towards further remediation works at Kerdiffstown.

On receipt of confirmation of 2020 total funding from my Department, Kildare County Council entered into a contract for final remediation work. The contract was awarded after the completion of a successful procurement competition. Significant work has already been completed on the site in making it safe and in securing appropriate access to allow for final remediation works to be carried out. The contractor for the final works is due to mobilise on site later this month and the contract is of 54 months' duration with project completion scheduled for 2025. Funding beyond 2021 will be determined in the context of the annual Estimates process and the funding requirements of the project.

Kildare County Council has a page dedicated to project progress on its website where regular up-to-date information on Kerdiffstown Park is provided.