Ceisteanna Eile - Other Questions
Primary Care Centres
8:10 pm
Stephen Donnelly (Wicklow, Fianna Fail) | Oireachtas source
I acknowledge the Deputy's strong advocacy work for the local healthcare facilities in his constituency and for the people he represents. I am pleased to be able to inform the Deputy that the development of five new primary care centres in County Clare is being progressed and, when completed, will add to the existing centre at Westbury. I acknowledge the Deputy's work in continuing to advocate to ensure these critical projects happen as quickly as possible.
The development at Station Road, Ennis is expected to be completed late in 2021 and to be operational in early 2022, while a planning application has been submitted to An Bord Pleanála for another centre in Ennis on the Tulla Road.
Planning permission has now been granted following an appeal for the centre at Sixmilebridge, and the developer is currently working to conclude outstanding matters. It is hoped to commence construction works in the coming months.
Priced offers from potential developers are currently under review for Ennistymon, while several potential sites have been shortlisted in the Kilrush area and a review of accommodation requirements for that area is being undertaken.
Unfortunately, it is not possible at this stage to provide an estimated operational date for these centres, other than for Station Road. I am determined that these projects progress as quickly as possible as part of our efforts to enhance primary care capacity. I look forward to working with the Deputy on these issues.
A total of 135 primary care centres are now operational across the country, and these modern, well-equipped and accessible premises are key to the development of primary care services in line with the vision of Sláintecare.