Saincheisteanna Tráthúla - Topical Issue Debate

School Accommodation

8:15 pm

Photo of Norma FoleyNorma Foley (Kerry, Fianna Fail) | Oireachtas source

As the Deputy will be aware, construction of Greystones community national school commenced on site in September 2018, prior to the emergence of issues in October 2018 in 42 schools constructed by the contractor involved, which has been the focus of the Department's schools remediation programme. For the duration of the work, the Department's project management technical advisory team included an architect, civil and structural engineer, fire consultant and others. These parties carried out regular site visits and inspections for the duration of the works. Matters raised by the contractor were tracked on an ongoing basis through fortnightly site visits and inspections by the project team to ensure the identified items were closed out.

The Department also retained a full-time on-site clerk of works for the duration of the project. Throughout the construction period the Department's project management team have used the appropriate provisions of the public work contract to secure the necessary assurance that the building is fit for handover prior to accepting it for handover. The Department will only accept the building and make it available for occupation by the school when it is completely satisfied that it is fit for handover prior to accepting it. The Department is taking appropriate steps to ensure this and engagement is under way between the Department and the contractor in this regard under contract. It is too early to say how long this engagement process might take but, as the process develops, my departmental officials will keep the ETB and school management informed of developments. I think it would only be appropriate to consider having a meeting further to that information becoming available to me.

Comments

No comments

Log in or join to post a public comment.