School Accommodation

5:35 pm

Photo of Norma FoleyNorma Foley (Kerry, Fianna Fail) | Oireachtas source

I again thank the Deputy for raising this issue. Scoil Chrónáin is an existing all-Irish co-educational primary school, under the patronage of the Archbishop of Dublin and centrally located in the village of Rathcoole. A building project to provide a new 16-classroom school plus a two-classroom special educational needs unit for the school is included in my Department's school building programme. The new building will be provided on a site adjacent to its existing site in Rathcoole, County Dublin.

This site is being acquired by my Department from South Dublin County Council.

Rathcoole Educate Together national school is a new English medium primary school being established in 2020 under the patronage of Educate Together. This new school will be an English medium, co-educational,16-classroom school, plus a two-classroom special educational needs unit. It will be located in a Department-owned site at Coolamber Drive, Rathcoole, County Dublin. Access to this site will require the construction of a new road which is currently being planned by South Dublin County Council. As the Coolamber site is not currently accessible and as the Department now has access to the land adjacent to Scoil Chrónáin, it was determined that the interim accommodation for Rathcoole Educate Together national school could be provided temporarily on that site.

The Department wrote to the board of management of Scoil Chrónáin on 19 March 2020 with regard to the proposed construction of a permanent school building for the school and outlining the Department's plans in this regard. The letter outlined that the Department was in the process of acquiring an additional site area adjacent to their existing site for this purpose.

Scoil Chrónáin was informed of my Department's intention to commence the architectural planning process for the construction of its new school building. The Department also outlined that in tandem with this it would also initiate the architectural planning process for the construction of the new primary school, Rathcoole Educate Together national school. The letter outlined that the building projects for both schools would be advanced in parallel.

The letter further outlined the need for my Department to provide interim accommodation to facilitate the new start-up school accommodation for Rathcoole Educate Together national school and that this interim accommodation was intended to be temporarily placed on the additional site area being acquired for Scoil Chrónáin. It outlined the process which was to take place, including lodging a planning application for the interim accommodation for Rathcoole Educate Together national school and also advised that the Department plans to move this temporary accommodation for the new school to its Coolamber Drive site as soon as site access is secured and in order to facilitate the construction of the permanent building for Scoil Chrónáin.

My Department had also intended to arrange a meeting with Scoil Chrónáin to explain these matters in more detail but then the Covid situation occurred which has prevented this meeting taking place to date. Now that the country is reopening for business, my officials will be in contact with Scoil Chrónáin to arrange that meeting shortly. I thank the Deputy for raising this matter.