I might read this document because substantial work has been done and it is important to put it on the record. It is probably one of the most visual elements of the preparations that we have done over the past while. Significant work has gone in to preparing us for a no-deal Brexit and for the fact that Brexit will mean change, even with a comprehensive future relationship. Work is complete on a number of facilities in Dublin Port, including 24 inspection bays, an additional Revenue turnaround shed, eight seal, check and transit booths, parking for 128 HGVs, and a live animal border control post. Work is ongoing on a number of additional projects, including alterations to existing facilities, and at some additional sites. There is a plan for a new site that covers an area of approximately 5.4 ha. It includes inspection facilities for customs, SPS, and health checks, import and export offices, and some 250 additional HGV parking bays. A step was taken today where the OPW published a notice that it is lodging an environmental impact assessment with An Bord Pleanála regarding these additional sites in Dublin Port.

Work on a border control post at Rosslare Europort is complete, with 38 HGV parking spaces, two seal, check and transit lanes for inspection bays, a Revenue turnaround shed, an export office and other offices. Much is done but work is continuing to try to enhance the live animal border control post inspection facilities that have been put in place.

I am pleased that work is complete at Dublin Airport, including the border control post facility with seven inspection rooms. We have ambient chilled and freezer storage areas and office accommodation for 20 staff. Substantial work has been done, with significant investment and building, and staff who will be needed to manage these being hired. Work is still ongoing and the objective is to try to get this work finished as quickly as possible. Covid-19 has created a challenge for us in this regard but anything that cannot be put in place permanently will of course be put in place temporarily by the end of this year as work continues.

Comments

No comments

Log in or join to post a public comment.