Ceisteanna Eile - Other Questions

North-South Interconnector

10:20 am

Photo of Seán CanneySeán Canney (Galway East, Independent) | Oireachtas source

The North-South interconnector is critical to improving the efficient operation of the single electricity market and increasing security of electricity supply across the island of Ireland. A resilient and well connected energy infrastructure is vital for Ireland's economic well being and the ability to respond to the future needs of energy consumers. In December 2016 An Bord Pleanála granted planning permission for the project in Ireland, while in January 2018 full planning permission was granted for the section of the line that lies in Northern Ireland. Both of the planning decisions have been subject to legal proceedings in each jurisdiction. In Ireland a Supreme Court appeal of the planning permission was dismissed on 19 February 2019.

In Northern Ireland, on 8 February 2019, the Department for Infrastructure asked the High Court to quash the planning permission given so the planning application can be re-determined under new legislation introduced by the Secretary of State for Northern Ireland in November 2018. The planning process in Northern Ireland is a matter for the authorities there.

There are currently a number of ongoing procurements in relation to the project being undertaken and managed by ESB Networks. In June 2019 ESB Networks awarded a framework contract for the design, test and supply of steelwork in relation to the project. However, under this framework there will be no supply of materials until the planning process in Northern Ireland is complete.

The earliest possible date for construction to commence is early 2020.