Dáil debates

Thursday, 4 July 2019

Ceisteanna - Questions - Ceisteanna ar Sonraíodh Uain Dóibh - Priority Questions

National Broadband Plan

9:40 am

Photo of Brian StanleyBrian Stanley (Laois, Sinn Fein) | Oireachtas source

This question is about the national broadband scheme. Will the Minister re-engage with Eir and the ESB regarding this plan? I am asking him to look again at the current process which, by any measure, is banjaxed. We are looking at a cost differential of €2 billion. Over the past couple of years, an overall cost of €800 million has become €3 billion. Worse still, members of the public who are awaiting broadband and have been promised it for a decade are no further on. The only broadband being provided is being provided by private operators regardless of the Department's plan. The current process is not fit for purpose.

Comments

No comments

Log in or join to post a public comment.