Schools Building Projects Status

6:40 pm

Photo of Mary Mitchell O'ConnorMary Mitchell O'Connor (Dún Laoghaire, Fine Gael) | Oireachtas source

I will try to answer the Deputy's final question first. There were design issues which need to be considered. This requires the design team to review the project to ensure compliance with new regulations, namely the near-zero energy building regulations.

Dublin and Dún Laoghaire ETB carried out a prequalification process at an earlier stage of the project. However, for a number of reasons, primarily of a legal nature, it has been decided to proceed with a fresh prequalification process. When Dublin and Dún Laoghaire ETB and its design team have completed the tender process, a tender report will be submitted to the Department with a recommendation for the award of the construction contract to the most economically advantageous tender submitted. The Department will examine the tender report and accompanying recommendation, following which the intention is that a contract will be awarded with a contractor moving onto site shortly thereafter.

The Minister, Deputy McHugh, wants to give assurances that the Department is committed to progressing this project as quickly as possible and to confirm that funding has been set aside to progress the building.

Comments

No comments

Log in or join to post a public comment.