Dáil debates

Tuesday, 18 September 2018

Ceisteanna Eile - Other Questions

North-South Interconnector

5:40 pm

Photo of Denis NaughtenDenis Naughten (Roscommon-Galway, Independent) | Oireachtas source

I propose to take Questions Nos. 48, 50, 80 and 83 together.

As the Deputies will be aware, in 2017 I commissioned two studies designed to address the main points of the motions passed by Dáil Éireann and Seanad Éireann, as well as key concerns expressed by those opposed to the development of the North-South interconnector, NSIC, as an overhead line. The first is an independent study to examine the technical feasibility and cost of undergrounding the interconnector. Three international experts in the field of electricity infrastructure development carried out a comprehensive analysis of international developments in undergrounding technologies since publication of the international expert commission's report in 2012. That was a key request of the representatives of the communities concerned about the proposed overhead line development. Two of the consultants appointed were members of the 2012 commission, while the third was a member of the 2014 independent expert group appointed by my Department to review key electricity grid projects. Therefore, all members of the commission were familiar both with the development of transmission grids across Europe, as well as the project in the context of Ireland's all-island electricity grid.

The North-South interconnector is critical to ensuring a safe, secure supply of electricity throughout the island of Ireland. It also supports the core objectives of European and national energy policy, namely, sustainability, security of supply and competitiveness. The project is the subject of legal challenges in both Ireland and Northern Ireland, with important legal dates imminent in both jurisdictions this month and next. EirGrid and ESB Networks are awaiting the outcome of the judicial challenges before they proceed to discharge their operational duties in the construction of the interconnector.

The second study is focused on the levels of compensation provided for land and property owners in proximity to high voltage transmission lines in a European context.​ This study was undertaken to consider a separate concern raised by public representatives at meetings with me on the impact of transmission lines on land and property values and the level of compensation paid in lieu of such impacts. Levels of compensation provided for land and property owners are considered to be a reflection of the impact of transmission lines on land and property values; therefore, this study, undertaken by KHSK Economic Consultants, analysed the compensation regimes in other European and selected international countries. Both studies have been completed and submitted to me.

In order to have the most up-to-date assessment of the implications of Brexit for the energy sector before bringing the reports to the Government, I sought the views of the energy regulator and electricity and gas transmission system operators on the implications for the electricity market in Ireland in the event of a hard Brexit, including for the single electricity market, SEM, timelines for the delivery of programmes such as DS3, delivering a secure, sustainable electricity system, and the North-South interconnector and continued secure cross-Border electricity trading across interconnectors.  The outcome of this analysis was submitted to my Department last week and is being considered. I have previously indicated to this House that it is my intention to bring the relevant reports to the Government for consideration prior to their publication. I expect to do this shortly.