Other Questions

Schools Building Projects Status

11:10 am

Photo of Richard BrutonRichard Bruton (Dublin Bay North, Fine Gael) | Oireachtas source

I understand the Deputy's concern. While there were some delays and unforeseen ground conditions, from the point of view of the design team the maximum delay should be six to eight weeks behind schedule and not the revised timeline. The local authority will be aware of the protections it has in the contract to ensure compliance and penalties in the event of failure. It is very clear the local authority, backed by the Department, will take a firm view in respect of the case because of the points the Deputy makes about the exposure both in terms of cost and the inconvenience this sort of delay will create for the pupils concerned.