Other Questions
Schools Building Projects Status
11:40 am
Richard Bruton (Dublin Bay North, Fine Gael) | Oireachtas source
This question relates to Gaelscoil Bharra in Cabra. The school building was handed over for occupation on 1 September 2017. However, as part of the contract for the project, some outstanding works remain to be completed at the adjacent Naomh Fionnbarra GAA Club, including completion of the all-weather pitch and car park reinstatement work. There are also a number of snags to be resolved in the school building, including issues with the heating system.
The design team had been in regular contact with Sammon since handing over the building in an attempt to get the snags resolved and the siteworks completed, but in spite of many promises from the contractor, particularly over recent months, no significant progress was forthcoming.
On 5 April 2018 Sammon entered into examinership and on 5 June the company was placed into liquidation. The Department then terminated the contract with Sammon Contracting under clause 12 of the public works contract.
There is a performance bond in place for this project and the Department has instructed the design team to liaise with the bondsman with the intention of calling on the bond to cover the costs of finishing out the works. The design team has been asked to produce a detailed scope of works which, as there is a live bond in place for this contract, can be used to request the bondsman to have the works completed without the need for a public tender process. This would be the quickest way of getting the works completed. If the bondsman is not prepared to complete the works then the design team will tender for a completion contractor to carry out the works and the remediation of the outstanding snags. Then the bill will be presented to the bondsman.