The national broadband plan, NBP, is about connecting people in rural areas, towns and villages across Ireland to high-speed broadband through a combination of commercial investment and State-led intervention. The NBP continues to act as a catalyst to commercial investment, with more than €2.75 billion invested by industry over the past five years. That is €1.8 million every single day.

Examples of the high rate of investment include Eir's rural deployment of broadband to 300,000 premises. Eir has surpassed its target of 101,000 premises passed by the third quarter of 2017. Siro continues its roll-out to 500,000 premises across 51 towns, with more than 100,000 premises now passed. Enet and SSE's plan to provide high-speed broadband to 115,000 homes in the west and north west is under way. Virgin Media continues its plans to expand its high-speed service to an additional 200,000 homes. Imagine has also committed to a deployment of fixed wireless broadband services particularly in rural and other more remote areas. A number of other operators have engaged with the Department on roll-out plans. The communications regulator's auction of the 3.6 GHz spectrum will also help pave the way for next generation connectivity for mobile customers.

When I was appointed Minister, just over 50% of homes and businesses in Ireland had access to high-speed broadband. Today the equivalent figure is 65% and by the end of next year, it will have risen to 77%. By the end of 2020, more than 90% of premises in Ireland will have access to high-speed broadband.

As a result of the national broadband plan we are witnessing a significant increase in the availability of high-speed broadband in Ireland. The Government is committed to leaving no one behind. Delivering connectivity to the 542,000 premises that fall within the State-led intervention phase of the national broadband plan remains a Government priority.

In the public procurement process, the NBP specialist team is continuing its evaluation of the detailed submissions of the two bidders, which were received last September. This is the last stage of the procurement process before moving to the final tender stage and subsequently the appointment of a preferred bidder or bidders. I fully appreciate that people want quality mobile and broadband connectivity as soon as possible and reiterate that this remains a priority for the Government, for me and for my Department. To help achieve that my Department will engage with the winning bidder or bidders to ensure the most efficient deployment as part of the NBP contract.