The building project for the Monasterevin primary school project is included on my Department's current six-year construction programme. The project is listed therein to commence construction in 2017.
The project was authorised to commence stage 2(b) of architectural planning on 30 June 2016. This stage includes the applications for planning permission, a fire certificate and a disability access certificate and the preparation of tender documents. The design team is currently working on the applications for these statutory approvals.
When all the relevant statutory approvals have been obtained the design team will submit the stage 2(b) report to my Department for review and when that review is complete the Department will contact the board of management with regard to the further progression of the project to tender and construction stages.