I am pleased that these questions have been asked. Often, the debate around rapid build becomes very negative because the initial rapid-build project - which was something of a pilot project - was delayed and encountered problems. The easy thing would be for me to say that I am not going to answer for my predecessor and all the rest of it. However, the reality is that what the previous Minister, Deputy Kelly, did constituted a genuine attempt to try to bring a new technology into building social housing a lot faster. A whole series of things happened that slowed the process down. That probably frustrated Deputy Kelly more than anybody else. This is actually a really positive story and I want to go through what we are doing now.

My Department is working closely with the four Dublin local authorities in relation to the rapid delivery programme. A total of 22 rapid-build units have already been delivered and are occupied. A total of 350 rapid-build houses will be advancing through various stages of delivery, including construction, by the end of this year. A further 650 rapid-build homes will be advanced in 2017, with another 500 units to be delivered in 2018.

It should be noted that Dublin City Council is currently advancing a number of rapid-build projects, including four in Finglas, Darndale, Cherry Orchard and Drimnagh, which will deliver a further 131 homes. These homes will be handed over to Dublin City Council on a phased basis from the end of the year and delivery will be completed early in 2017. My Department is working closely with the council to expedite delivery.

In addition to these four projects, further work is under way across the four local authorities that will bring to 350 the total number of rapid-build homes advancing through various stages of delivery, including construction, by the end of the year. The additional sites in question are in Dublin city, Dún Laoghaire, Cherry Orchard, Tallaght, Blanchardstown and Balbriggan. Construction dates will be finalised in the context of completion of procurement and award of contracts. Sites are being identified and planning requirements advanced for a further 650 rapid-build homes in 2017 across the four Dublin local authority areas and also in Louth, Wicklow, Kildare, Meath, Cork, Waterford, Galway and Limerick. This will ensure that the commitment in Rebuilding Ireland to deliver 1,000 rapid-build homes in 2016 and 2017 is met.

The standard delivery timeframe for a traditional social housing construction project from inception to occupation can range from 12 months to three years, depending on the complexities of the project. All social housing construction projects, including rapid-build projects, must follow certain basic steps before construction can commence.

There has been significant pressure to ramp up delivery, which local authorities have been responding to positively. However, there are requirements, such as in the context of procurement, that have to be adhered to and that, in some instances, have caused delays. Notwithstanding this, I am confident that all parties are endeavouring to move the programme forward speedily.

We now have finality from the Government office of procurement to put a central procurement list together that local authorities from anywhere in the country can simply pick companies from, because those companies have been through the procurement tests, certification and so on.

I know that this has got off to a bad start in some ways. I have regularly had debates on that in media and elsewhere. However, I actually think a lot of private estates are going to be built with this technology as well. Rapid build is simply a different way of constructing houses.

Much of the assembly is done off-site in a factory-style setting where pieces are craned in and put together, which allows one to build houses faster and potentially create economies of scale.