Dáil debates

Wednesday, 6 July 2016

Topical Issue Debate

Dublin Airport Authority

2:35 pm

Photo of Shane RossShane Ross (Dublin Rathdown, Independent) | Oireachtas source

I thank the two Deputies for once again bringing this particular subject to my attention. I met the DAA last week on the same day as it was making the presentation in Buswells, and I put some of those points to them to take away.

As the Deputies will be aware, DAA has a statutory responsibility to manage, operate and develop Dublin Airport, including the provision of infrastructure necessary to meet existing and future demand, such as the north runway project. The DAA was granted planning permission in 2007 for a second parallel runway and the necessary lands have been preserved for such a project since the 1960s. However, due to the downturn in the economy, the project was not progressed. Given the significant increase in passenger numbers at Dublin Airport in recent years and the projected traffic growth in future years, it is clear that a second parallel runway is needed.

Against this background, the DAA announced its decision to proceed with the development of the north runway project in April 2016. The DAA expects construction to commence in early 2017 with the runway operational by 2020. The planning permission granted for the second parallel runway in 2007 had 31 conditions attached and is valid for ten years. I should point out that planning matters are the responsibility of the relevant local authority, Fingal County Council in the case of Dublin Airport, or An Bord Pleanála, as appropriate. Two of the conditions relating to noise operating restrictions are of particular concern to DAA in that they would result, DAA states, in operations across the entire airport being restricted during the night, between 11 p.m. and 7 a.m., to limit noise impacts on the surrounding area. The constraints are such that flights at the airport in the peak hour between 6 a.m. and 7 a.m. would have to be cut back by approximately one third. Over the last number of months, DAA has been examining the scope of a further environmental impact statement, EIS, for the purpose of seeking a review of the operating restrictions foreseen for Dublin Airport under the existing planning permission for the north runway. I understand that a public consultation has now commenced to explain why changes are being sought to the two planning conditions and to provide an opportunity for stakeholders to contribute to the content of and the approach to be adopted in the EIS process. Regarding the issue of noise, EU Regulation 598/14 relating to the introduction of noise-related operating restrictions at EU airports entered into force last month. This regulation sets out the process to be followed when deciding on noise-related operating restrictions and involves consideration of all potential aircraft noise mitigation measures. The regulation provides for consultation with interested parties, including local residents living in the vicinity of the airport. The new noise regulation presents an opportunity to establish a modern, cohesive and measured approach to the management of noise at Irish airports which is capable of delivering the best outcome for all stakeholders. With a view to ensuring the most effective implementation of the new noise regulation in Ireland, my Department is currently working on the detailed technical arrangements to be set down in regulations that I intend to make in this regard as soon as possible. Finally, I met with senior officials of DAA last week to discuss a number of issues, one of which was the north runway project. The DAA advised that it is very conscious of balancing the national needs in delivering an essential piece of infrastructure while minimising impacts on local communities.

In this regard, DAA briefed me on its engagement with residents on the project and outlined the various strands of work underway on the project, which include the discharging of pre-commencement planning conditions relating to noise mitigation measures, such as the voluntary insulation and house buyout scheme which will be available to residents whose houses are most impacted.

In addition, they spoke about the substantial public consultation and communications programme they have commenced which will continue as the north runway project develops. I understand that these information sessions will provide relevant and accessible information to stakeholders about the planning permission that has been granted, what will be built, when it will be built, how it will be built and how any issues will be addressed.

Comments

No comments

Log in or join to post a public comment.