I thank the Deputy for raising the matter. As she is aware, Lusk community college is a co-educational post-primary facility under the patronage of Dublin-Dún Laoghaire Education and Training Board. The second phase of the major building project for Lusk community college will provide for a new-build extension to cater for an additional 650 pupils, a special needs unit, a physical education, PE, hall with fitness suite and changing facilities and ancillary accommodation, including a school library.
The first phase which was completed under the Department’s design and build programme provided a building to cater for 350 pupils. This first phase was completed in July 2013 and the school opened in September 2013. The overall school, once complete, will cater for a long-term projected enrolment of 1,000 pupils.
The design team for the project was appointed in January 2012 and the project was authorised to commence architectural planning. The project is included in the six-year construction programme which was announced in November 2015. The building project for Lusk community college is now at an advanced stage of architectural planning - stage 2b, detailed design - which includes the preparation of tender documents. Planning permission for this project was granted on 2 March 2016. Fire safety and disability access certificates were obtained in 2015.
The stage 2b report has been completed by the design team and is being co-ordinated by the education and training board for submission to my Department for review in the coming days. Upon completion and submission of the stage 2b report and tender documentation, my Department will carry out its review and, subject to no issues arising, will then revert to Dublin-Dún Laoghaire Education and Training Board with regard to the further progression of the project. However, until the stage 2b report has been received and assessed, it will not be possible to provide a specific indication of the timeframe for the progression of the project to tender and construction. That is the current position.