Dáil debates

Tuesday, 10 February 2015

Ceisteanna - Questions - Priority Questions

Waterways Issues

2:15 pm

Photo of Heather HumphreysHeather Humphreys (Cavan-Monaghan, Fine Gael) | Oireachtas source

At the outset, I should make it clear to the Deputy that, contrary to the suggestion in his question, the Department of Culture, Arts and Leisure in Northern Ireland is neither awaiting approval for, nor proposing to meet, the capital cost of the first phase of the Ulster Canal project. The facts are that in July 2007 the North-South Ministerial Council agreed to a proposal with the then Irish Government to proceed with the restoration of the Ulster Canal between Clones and Upper Lough Erne and, in that context, the Government agreed to cover the full capital costs of the project, estimated at that time to be of the order of €35 million.

Planning approval for the project has been secured from the relevant authorities in the two jurisdictions - namely, Cavan County Council, what was Clones Town Council, Monaghan County Council and the Northern Ireland planning service. An updated business case was recently completed for my Department, and options for progressing the project within the current fiscal constraints are being explored. This includes the option of enabling access from Upper Lough Erne to the International Scout Centre at Castle Saunderson near Belturbet in County Cavan at an estimated cost of some €2.5 million, including VAT as appropriate. I hope to be in a position to bring the matter forward for further consideration by the Government in the coming weeks.

Comments

No comments

Log in or join to post a public comment.