Dáil debates

Wednesday, 8 October 2014

Topical Issue Debate

Flood Prevention Measures

1:35 pm

Photo of Simon HarrisSimon Harris (Wicklow, Fine Gael) | Oireachtas source

I thank Deputy Coonan for raising the Templemore flood relief scheme today and on a number of occasions during the two and a half months I have been in office. I accept it is a very important issue to him and his constituents. I had an opportunity to meet the Deputy and a number of residents in Templemore prior to my appointment to my current post and I know the importance of the issue for the people of Templemore. Before I outline the detailed response to the question, I wish to make clear that as Minister of State with responsibility for the OPW, I am fully committed, as is the OPW, to the delivery of the Templemore flood relief scheme. The funding is in place and it is a priority project which will be delivered.

I will provide some background, much of which the Deputy outlined, but I will put it on the record.The proposed flood relief scheme works for Templemore include the construction of a new bypass channel, along with road and property access bridges, flood defence walls and embankments, and some channel widening downstream of the town. As Deputy Coonan outlined, the proposals were placed on formal public exhibition from 30 January to 4March 2009. Additional engineering and route complexities arose in relation to a section of a culvert that is a key element of the scheme. Two alternative routes had been identified for this culvert section in the initial design stage of the project. The route which was technically preferred would necessitate the demolition of a commercial premises. While the other route would involve a significant impact on commercial properties, it would not involve permanent closure of the businesses. For that reason, the latter option was chosen and shown in the proposals that were exhibited to the public.

During subsequent investigation, further information and details emerged on the costs associated with the exhibited route, including potential claims for compensation from property owners affected by the works. There was also further clarification on the costs associated with the other, non-exhibited route, involving the closure of a commercial premises. This new information necessitated a full review of the economic rationale for each option involving a detailed analysis of the comparative costs of the two alternatives. The review took account of all likely costs, including construction and site remediation costs, property acquisition costs for the technically preferred route, and compensation to other property owners impacted. Following the review, it was concluded that the technically preferred route should be proceeded with. As that represented a significant change from what was included in the scheme that had been previously exhibited, the proposed alternative route was displayed to the public on 28 March this year, as Deputy Coonan outlined, and it was broadly well received.

In further developing the amended proposals, consideration was given to whether the full flow in the existing channel should be diverted into the bypass channel. For technical reasons it is proposed that the existing channel will continue to carry normal flows and the bypass channel will carry flood flows only. An issue also arose in relation to a combined sewage and storm water overflow pipe in the Church Road area of Templemore which is in the path of the proposed bypass. The OPW is in discussions with Irish Water regarding works necessary to circumvent the pipe. It is expected that this matter will be resolved satisfactorily and that it will not delay progression of the scheme.

The next step is that the amended proposals will be put on formal public exhibition, in accordance with the Arterial Drainage Act 1945. That will take place early in 2015. Any observations received from the public or other stakeholders will be taken into account, as appropriate. Following that, confirmation or statutory approval of the scheme will be sought from my colleague, the Minister for Public Expenditure and Reform. Pending completion of the exhibition and confirmation from the Minister, Deputy Howlin, it is not possible to state definitively what the timeline for delivery of the scheme will be. However, the new scheme will be exhibited early in 2015. The OPW fully recognises the need to implement the scheme for Templemore as a priority. I, personally, and the OPW will do all we can to ensure the scheme commences as soon as possible. To that end, if the scheme is confirmed, the construction work will be carried out by the OPW's direct labour force. The decision will dramatically reduce the time required to commence the project because we will not have to go through a lengthy tendering process, which therefore provides an opportunity to claw back some time.

I can confirm that provision has been made for the Templemore scheme in the OPW's capital budget allocations for flood risk management to 2016. The funding is in place and the scheme is an absolute priority. We must get the scheme exhibited. I am committed to doing everything I can. When I visit Templemore with Deputy Coonan, it will be to unveil the scheme, which will have started at that stage.

Comments

No comments

Log in or join to post a public comment.