Dáil debates

Thursday, 21 November 2013

Topical Issue Debate

Electricity Transmission Network

6:15 pm

Photo of Pat RabbittePat Rabbitte (Dublin South West, Labour) | Oireachtas source

I would like to thank the Deputies who have given me an opportunity to make these remarks about this issue. I do not know why it took three weeks for Deputy Phelan to get it on the agenda. I was out of the country on energy business over the last couple of days, but other than that, I am available to deal with the queries any time they are raised.

EirGrid's Grid25 national programme, and specifically the grid link infrastructure project, is vital for future socioeconomic progress in Ireland. The grid link project is a key initiative under Grid25. The project consists of a new 400 kV power line linking Leinster and Munster. Without this project, the grid in the south and east of Ireland would not be sufficient to meet the region's future electricity needs. The grid link project will help enable a secure supply of electricity for the region well into the future. It will empower growth in the south and east of Ireland and involve an estimated €500 million investment. It will also enable Ireland to meet its 40% renewable target and reduce our reliance on imported fossil fuels.

In the Government policy statement, to which Deputy Phelan referred and which I published in July 2012, the imperative for the State companies and all developers of energy projects of early, transparent engagement and consultation with local communities and stakeholders was emphasised. Currently the EirGrid project team is undertaking detailed analysis of the study area in order to identify the best possible corridors for development. As part of this process, on 3 September EirGrid published the first state report on the grid link project, identifying a number of overhead route corridor options for the new 400 kV power line. The publication of that report coincided with the beginning of a twelve week public consultation period.

I am aware that EirGrid is fully committed to extensive public consultation and that the company has been engaging in a comprehensive process in regard to the grid link project which has involved opening regional information centres, a lo-call project information telephone line and local radio advertising, backed up by national and local print advertising. EirGrid opened five project information centres at Midleton, Carlow, New Ross, Carrick-on-Suir, and Kilcullen. I understand that 33 open days were held within the project area over the last 16 months and that since autumn 2012, the grid link project team has visited marts, shopping centres and agricultural shows, attending over 120 events where thousands of stakeholders have engaged with the team and had an opportunity to inform themselves about the programme in more detail. I am also aware that the project team briefs and updates county councils, town councils, chambers of commerce and other local organisations and national and local politicians regularly, and have done so since the launch of the project in April 2012.

The current consultation process is a key opportunity for public input, as no decisions have been made regarding the final route of this electricity line. EirGrid has stated that it will fully take on board information and views about the grid link project, which is still at an early stage. Ultimately, it will fall to An Bord Pleanála to determine whether the views expressed have been adequately taken into account in the final project design.

EirGrid, under its licence as the transmission system operator, is obliged to plan the electricity transmission network in the most safe, secure, economic and reliable way possible. It has set out in its information brochure for the current consultation process the rationale for preferring overgrounding to undergrounding generally for this project. In the same document it states it is recognised that underground cabling may have to be considered to mitigate identified environmental constraints for the project and that this will be thoroughly investigated during the project development process.

I understand the concerns raised about the various aspects of grid development and there should be a full opportunity to explain all aspects of the Grid Link and other projects under Grid25. I am aware that the Joint Committee on Transport and Communications met yesterday with a number of anti-pylon community groups from the south east, north and north east regions which raised their concerns about grid development. The committee intends to write to EirGrid on foot of the discussions and meet representatives of the company and my Department at a meeting scheduled for 4 December.

Comments

No comments

Log in or join to post a public comment.