Thursday, 27 June 2013

6:30 pm

Photo of Leo VaradkarLeo Varadkar (Dublin West, Fine Gael) | Oireachtas source

This question is about plans to develop a rail service to Navan. I will be officially opening the new Hansfield station tomorrow. This is the final element of the first phase of the extension of the rail line to Navan, from Clonsilla to the M3 Parkway.

The Government’s policy on capital investment is set out in the document, Infrastructure and Capital Investment 2012-16: Medium Term Exchequer Framework. Under the framework, the extension of phase 2 of the Navan line has been postponed for consideration in advance of the next capital programme. Overall, the level of Exchequer funding available for the development of transport infrastructure has been greatly reduced in recent years.  As this reduced level of funding will not allow for significant investment in new public transport infrastructure, the Government's focus is on aiming to make better use of the existing system and resources. Funding has been prioritised to ensure the maintenance of the existing infrastructure and advance a small number of projects which can add value to the existing network.

Despite the reduced level of funding available, my Department has allocated over €135 million towards the rail network this year. The bulk of this funding will go towards renewals and maintenance under the railway safety programme and enhancement projects such as signalling, the provision of automated ticketing facilities and the removal of level crossings. For example, work will shortly commence on the removal of Reilly’s level crossing on the Maynooth line which will be of benefit to passengers travelling on phase 1 of the rail line to Navan.

Comments

No comments

Log in or join to post a public comment.