Dáil debates
Thursday, 12 January 2012
Ballymun Regeneration Programme
4:00 pm
Jan O'Sullivan (Limerick City, Labour)
I thank Deputy Lyons for raising this issue. As he stated, both he and I have a strong interest in regeneration. I begin by reiterating my own commitment and that of my Department and the Government to seeing the regeneration of Ballymun successfully completed.
Ballymun regeneration is by far the largest regeneration project ever undertaken in this country, with a capital investment of more than €700 million over the past 15 years. Over that period, the project has delivered over 1,600 social housing units, 105 voluntary housing units and some 1,200 private and affordable units. A further 215 units are under construction at present and another 25 were recently approved to go to tender. Six of the 7 landmark towers have been demolished and almost all of the original 2,800 flats are either already demolished or are under contract to be demolished. In addition, the project has seen the delivery of a range of new infrastructure from roads and other services, to new parks, neighbourhood centres and state of the art community facilities. It is important to note that this substantial investment has not been limited to physical infrastructure. In line with the principles of regeneration, Ballymun Regeneration Limited, BRL, has also sought to address the causes of disadvantage through a programme of social interventions, including the very successful Axis Theatre and bringing much needed job opportunities to the area, such as IKEA and through the Rediscovery Centre.
The Ballymun regeneration programme has now moved into its completion phase. My Department is working closely with BRL and the City Council to ensure it is completed properly, on time and in a manner that protects the existing investment. I note Deputy Lyons' point in this regard. These projects are very complex and require a broad vision beyond just the replacement of houses. For this reason, our actions to complete the project at Ballymun are as important as those to commence it.
That said, after 15 years the community profile has changed and it is clear that the original number of social housing units proposed under the original masterplan may no longer be needed. As such, it is my intention to ensure that the projects planned and underway - some 250 units - will meet the remaining housing needs of the community as quickly as possible. I am particularly concerned to ensure that those 26 households living in the worst accommodation are rehoused as a matter of urgency. In addition, I would like to restate my commitment to the social and economic regeneration of the area, which will have to continue after the physical works are completed. In this regard, I will be looking to my Government colleagues to ensure a whole of Government approach is taken and sustained.
I note the particular area to which Deputy Lyons referred.
No comments