Thursday, 5 November 2009

8:00 am

Photo of Noel DempseyNoel Dempsey (Meath West, Fianna Fail)

Earlier this year, my Department allocated €404 million to Iarnród Éireann for investment in the development of the rail network and railway safety. Of this, €90 million was allocated to the railway safety programme.

As is normal for a programme of the range and complexity of the public transport capital programme, a number of adjustments were made during the year and an additional €2 million was allocated to Iarnród Éireann in July, followed by an additional €7 million in September, arising from other areas of the programme where spending was lower than expected. In addition, Iarnród Éireann was able to re-allocate funding to the railway safety programme from adjustments to its own investment programme such as revisions to the payment schedule for new rolling stock.

These re-allocations allowed an increase in the Exchequer provision for railway safety to €107 million for the current year. Iarnród Éireann undertook the repair of the Malahide viaduct from within this increased provision. The total estimated cost of repairing the viaduct itself will be in the order of €4.5 million to €5 million.

I understand from Iarnród Éireann that it will be in a position to re-open the line later this month once approval is received from the Railway Safety Commission. I welcome the speedy re-instatement of the viaduct.

Comments

No comments

Log in or join to post a public comment.