The report is already available on a website. Have the Deputy and his colleagues not read it? The Deputy is asking me to make the report public, but it already is in the public domain. He should do his homework. Of course I knew the population would increase, but I was not in Government or on Dublin City Council. I was on the local authority and I made amendments because it was a reserve function. In the body of the report, although not in its conclusions, it is clearly stated that the nitrogen removal recommended unanimously by the elected representatives across all parties was ignored by the city council. That is a grave disappointment to me.

The design, build and operate contractor made a claim for additional final contract costs of €171.8 million arising from the disputed items including changes in electrical equipment standards and the higher load to the plant. Under the circumstances the €35 million I managed to negotiate down to was a very good cost saving measure and dealt with the odour problem, which was the main issue for residents of the area.

Comments

No comments

Log in or join to post a public comment.