Dáil debates

Wednesday, 20 February 2008

1:00 pm

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)

I thank the Leas-Cheann Comhairle. Where accommodation is needed at very short notice, however, a temporary solution can be the only option. Such accommodation may also be used where the need is short term, such as when a school requires a temporary building while it is awaiting the completion of construction of permanent facilities. Last year, only 5% of the total investment in school buildings went on the rental of temporary accommodation.

This year, almost €600 million will be invested in school buildings and construction work will take place which is expected to provide permanent accommodation for about 20,000 pupils when complete. In the past, newly-recognised schools have generally had to open in temporary accommodation. I have been anxious to move away from this approach in developing areas and this year we are working hard to open as many new schools as possible in permanent accommodation.

Department officials have been working in partnership with local authority staff to acquire sites needed for new schools next September. Considerable effort has also been invested in pre-planning discussions with a view to ironing out any difficulties that might otherwise have been experienced at planning permission stage. I also held productive meetings with several county managers and their senior planners and appreciate the effort that they have put into working with us on this matter.

Sites for each of the September 2008 projects have been identified and site master-plans have been developed by the technical teams. Our aim, where possible, is to put permanent solutions in place on a phased basis to meet the immediate September 2008 needs with a second phase to follow as required.

Additional information not given on the floor of the House.

Permanent solutions will be possible where a long-term site has been secured.

A significant amount of building work on the new schools is being done off-site. The successful tenderers for the construction of each individual project have been notified.

Project teams which were recruited from the private sector in October 2007 have been tasked with preparing the planning applications, undertaking the necessary surveys and overseeing the delivery of the schools on each site. To conclude, expenditure on temporary accommodation has tended to represent a very small proportion of the overall investment in school buildings in recent years. The use of prefabs is avoided where possible but sometimes they can be the only feasible option. We are now working to ensure that, where possible, new schools in developing areas will open in permanent accommodation from the start.

Comments

No comments

Log in or join to post a public comment.