Dáil debates

Tuesday, 22 March 2005

3:00 pm

Photo of John O'DonoghueJohn O'Donoghue (Kerry South, Fianna Fail)

During the severe weather conditions experienced in the west Dublin area on New Year's Day 2005, damage was caused to the National Aquatic Centre at Abbotstown. The roof of the 50 metre pool and diving pool and the roof of the leisure water area were both damaged and, in addition, damage occurred to lights and fittings around the complex. This has resulted in the National Aquatic Centre being closed to the public while the building was being made safe, the damage assessed and repairs undertaken. Fortunately, nobody was hurt as the centre was closed for the holiday period.

On 2 January, Rohcon Ltd., the company responsible for the design and construction of the National Aquatic Centre, carried out some initial repair work to make the building safe. During the days immediately afterwards, Campus Stadium Ireland Development Ltd. was at hand to manage and oversee the response to the situation. CSID's first priority was to ensure the safety of the general public and anybody using or working in the facility. They were also focused on ensuring that the damage was accurately assessed by the insurance assessors, that liability for the repair work was established, that repairs would be carried out as quickly as possible and that the debris in the facility, and in its vicinity, was safely removed. Because of the weather conditions, in particular the high winds experienced during January, it was not safe to access the roof until towards the end of the month and this delayed the work of the engineers who examined and reported on it.

At the request of my Department and in consultation with CSID, the Office of Public Works engaged Kavanagh Mansfield & Partners, Consulting and Structural Engineers, to provide an independent, expert opinion. They were requested to examine the damage and to provide a report. In addition to this independent report, a separate report was prepared by engineers on behalf of the company carrying the insurance cover on the NAC.

Following the presentation of their report, Kavanagh Mansfield & Partners were appointed by CSID in regard to the development and implementation of the appropriate remedial works for the storm damage. A copy of the independent report has been given to Rohcon Ltd. and a schedule of remedial works has been prepared on behalf of Rohcon and submitted to CSID. This will ensure the centre is restored to the highest standards. The costs of the storm damage will not accrue to the State. Detailed discussions have been taking place with the various parties involved to resolve the situation as quickly as possible. CSID has confirmed to me that remedial works to the National Aquatic Centre effectively commenced yesterday, Monday, 21 March, when Rohcon, its roofing sub-contractors and consulting engineers responsible for the work were on the roof. These parties are now finalising, in consultation with CSID's engineers, the details of the schedule of works to be undertaken to repair the damage. While it is difficult to be precise about how long the work will take, my best information as of now is that it should be completed in six to eight weeks. The contractors have promised a firm estimate for completion of the repair work later this week.

Additional information not supplied on the floor of the House

I wish to reiterate that I want to see the National Aquatic Centre reopened at the earliest possible date. Although I fully understand the frustration of the staff and the general public, including members of facility clubs, at the continued closure of the centre, the alternative scenario, that of opening the centre while there was a risk to people using the facilities, is not an option that anybody would be prepared to contemplate. Therefore, the inconvenience of the centre being out of commission is, in my opinion, the lesser of two evils. Over the past months, CSID has put a considerable effort into working with the various parties to have the centre reopened as quickly as is feasible in the context of finding a safe solution. I am satisfied that this will be achieved.

Comments

No comments

Log in or join to post a public comment.