Tuesday, 2 November 2004

3:00 pm

Photo of Martin CullenMartin Cullen (Waterford, Fianna Fail)

I announced on 21 October 2004 that the operational height of the Dublin Port tunnel would not be changed. My decision was based primarily on safety grounds, but cost and time delays to the opening of the project were also factors.

The options for increasing the height of the tunnel were considered by the National Roads Authority, independent consultants, Atkins, and Dublin City Council. In addition, the contractor, the NMI consortium, priced the work that would be involved in increasing the height of the tunnel. It was clear from that work that raising the height of the tunnel would not be justified having regard to safety considerations and additional cost and delay factors.

The safety issues concerned reducing lane widths, which would, in the context of a tunnel carrying a very high percentage of heavy goods vehicles, including fuel tankers and other hazardous cargoes, constitute a reduction in overall tunnel safety. It is intuitively apparent that wider traffic lanes offer greater vehicle separation than narrower lanes. As for increasing the kerb height, it is apparent, on both an engineering and intuitive basis, that a 150 mm kerb must represent a safer provision than one of 200 mm. It is the NRA's position that the lower kerb height is preferable from a safety perspective. Also considered were overheight heavy goods vehicles, HGVs, on the existing national road network and the implications of facilitating higher vehicles through the tunnel than the national motorway and road network can safely accommodate. Bridges and other structures on motorways and national roads are not designed to cater for vehicles higher than the current tunnel height, and safety concerns would arise over the discharge of such vehicles from a revised tunnel onto the national road network. Increasing the height of the tunnel would mean substantial potential additional costs of at least €33 million to €65 million, and at least a seven month delay to the completion of the tunnel.

I understand from the NRA that the construction of the tunnel is expected to be complete in December 2005. Extensive arrangements are in place to meet the concerns of local residents about the impact of the project. These were of particular value during the tunnelling, which is now complete. These arrangements included pre and post construction property surveys, the use of vibration monitors to monitor vibration from the works, and settlement surveys. Any damage attributable to tunnelling works is covered by the property protection guarantee issued by Dublin City Council. I am informed that over 176 claims have been received, of which 155 are subject to ongoing negotiation, claiming in most cases minor damage to properties. An independent loss adjuster has assessed or is in the process of assessing these damage reports and I am advised that any verified damage connected with the tunnelling will be made good by Dublin City Council.

Comments

No comments

Log in or join to post a public comment.