Photo of Robert TroyRobert Troy (Longford-Westmeath, Fianna Fail)

The projected cost to Revenue was €81.255 million, or 34.43%, but what we have paid to date is €68.51 million. The OPW has requested a further €5.88 million, with approximately €1.578 million for 2026. If we add €68.1 million to €5.8 million, plus €1.6 million due next year, the project is actually coming in below what it was projected to cost Revenue at the initial stage, which was €81.255 million.