Select Committee on Finance, Public Expenditure, Public Service Reform and Digitalisation, and Taoiseach
Estimates for Public Services 2025
Vote 7 - Finance (Supplementary)
Vote 9 - Revenue Commissioners (Supplementary)
2:00 am
Robert Troy (Longford-Westmeath, Fianna Fail)
The projected cost to Revenue was €81.255 million, or 34.43%, but what we have paid to date is €68.51 million. The OPW has requested a further €5.88 million, with approximately €1.578 million for 2026. If we add €68.1 million to €5.8 million, plus €1.6 million due next year, the project is actually coming in below what it was projected to cost Revenue at the initial stage, which was €81.255 million.