Ms Angela Denning:
I cannot answer that here. We are in the middle of the Estimates process and it will have to go through the process. What I can say is that from the 2024 budget, we spent €75 million on pay. We spent €47.8 million on non-pay. IT spend was just more than €20 million. Our capital court houses were €5.7 million. Our public-private partnership, PPP, unitary payments for the Criminal Courts of Justice were €23.8 million-----