Mr. Mick Mulhern:
On the PPP, we are currently looking at an alternative delivery route for bundles 3, 4, 5 and 7 which have 16 Dublin City Council sites in them. It is fair to say, as I explained earlier, that bundle 3 is delayed. That was due to start on-site in July. We are trying to identify what the preferred route is. That could be up to 12 months of a delay. Bundle 4 is likely to have some delay, but not as bad as bundle 3. We hope the bundles after that will just follow in line with a new delivery route that is identified. There will be some delay but it is not across all bundles. Basin View is in bundle 5 and has planning permission. We had commenced some very early de-tenanting and we are working with the allocations team and the local community on that. There may be some specific cases that still need to be progressed.