Mr. Paul Benson:
But there was a contract with the preferred tender, that is, design and build. He has to carry out site investigations due to his detailed design. That work will be done by the consortium, but the actual contract to build the units is a separate process. That requires approval from the Department of housing, which was the funder of it, to go ahead. The has been made - it is not to proceed.