National Paediatric Hospital Development Board and Children's Health Ireland: Discussion
2:00 am
Mr. David Gunning:
No, for delay. The money is all in the delay. There are 16 claims that amount to approximately €800 million and each of them is for a component of the delay that BAM claims the employer - the State side - has delayed its progress from August 2022 up until now. It accounts for individual components of that or contributors to it or whatever. As I mentioned, there is duplication and triplication even in those 16 claims, but that is what we are defending.