Mr. David Gunning:
It is entirely an indicator of the progress of the contractor. The contractor is paid for the work that it does. The level at which it has achieved is way below what we would have expected would have happened if it was delivering on the timeline to which it had committed. Therefore, it is purely a lagging indicator of progress.