Mr. David Gunning:

We have already mentioned that we have had 15 different programmes with different completion dates. However, on a monthly basis, under the contract, the contractor is required to provide a monthly programme update. We receive what you might call a mini programme on a monthly basis. Then, if the programme is deemed to go out of compliance, as in the completion date is no longer achievable, we require the contractor – the employer’s representative on behalf of the State, if you like-----