Oireachtas Joint and Select Committees

Thursday, 22 May 2025

Public Accounts Committee

National Paediatric Hospital Development Board and Children's Health Ireland: Discussion

2:00 am

Mr. David Gunning:

The contract value is the contract with BAM - that is the €910 million. Then, in addition, there is the cost of the design team, the development board's costs and all the advisers and various other costs that come into this. I commented earlier about the project going on for three years longer than anticipated. Our costs on a monthly basis are approximately €2 million. Every month that goes by is an additional €2 million on the project costs for the development board and the design team.

Comments

No comments

Log in or join to post a public comment.