National Paediatric Hospital Development Board and Children's Health Ireland: Discussion

2:00 am

Mr. David Gunning:

No, there were no blank cheques. Where we are as of right now is that when that initial budget of €1.433 billion for the NPHDB component was approved - this is all set out in that PwC report - certain areas were not included within that sum. To pick out one example, I do not think people anticipated at the time that there would ever be Brexit, a war in Ukraine or the level of construction inflation we have experienced. The contractor agreed to pay for the first 4% of any inflation and to absorb that cost and the figure above 4% was the State's cost. The construction inflation we have had to pay to the contractor over and above what was agreed has cost the State roughly €50 million over the period until the middle of 2022. Inflation is one element-----